Wednesday, July 18, 2012

2 die and 8 injured in Downtown Line accident

10 workers were working on the casting of permanent roof slab between the new and old sections of Bugis MRT station. Eight were on top of the scaffolding supporting the formwork, while two others were working below.

Then, at 6.50am, the scaffolding 4m below the surface collapsed while workers were pouring concrete into the formwork.

Click here to find out more!
Eight workers were injured and sent to Raffles Hospital, and two were missing. At 9.50am, LTA said that the two workers were still unaccounted for.

Over 50 SCDF rescuers and police officers arrived at the accident site with LTA employees, construction workers and two search dogs.

Collapsed bars and planks from the scaffolding covered the underground structure like a web. Rescue workers made their way through the 30m by 5m, and 15m-deep site by cutting metal bars with a blow torch.

At around 10.40am, a body was spotted trapped under fallen scaffolding and submerged in wet cement. It took workers an hour to extract the body. At noon, the death of one worker was confirmed.

Workers from the Public Utilities Board were also seen checking sewage pipes near the site, while police officers were spotted carrying a body tent, which is usually deployed in cases where deaths occurred.


Source: http://www.asiaone.com/Motoring/News/Story/A1Story20120718-359829.html